Construction Updates: July 2018

We're in Week 19 of construction and we're excited to announce that the crane is now fully established and the basement is nearing completion!

We’re in Week 19 of construction and we’re excited to announce that the crane is now fully established and the basement is nearing completion!

Here’s a summary of the progress so far:

  • Basement floor slab is complete
  • Basement blockwork is now 90%
  • Basement backfill to conclude next week
  • Ground floor formwork has commenced
  • First ground floor slab preparation is underway

We're in Week 19 of construction and we're excited to announce that the crane is now fully established and the basement is nearing completion!

Here's a summary of the progress so far:

  • Basement floor slab is complete
  • Basement blockwork is now 90%
  • Basement backfill to conclude next week
  • Ground floor formwork has commenced
  • First ground floor slab preparation is underway